Statement from Planning Inspectorate PR office, Bristol: "The current state of play is that a site visit took place on April 10th.
"The case is to be determined by written representations so there will not be an in person hearing.
"The next step is for the Inspector to consider all the written submissions and prepare their Appeal Decision which will be uploaded to the Appeals Casework Portal when it is issued; this will take several weeks although it is difficult to provide an exact timescale as every case is different."
Updates can be viewed on its Appeals Casework Portal using the final 7 digits to search:
APP/P2365/W/23/3324305
Case Search (planninginspectorate.gov.uk)
A few months ago a large party from Hyundai - which is bankrolling the project - were at the site reviewing progress.